|
To: INTERESTED
PARTIES OF UNIONTOWN IEL SUPERFUND SITE 11/17/05
Re: LEGAL
DOCUMENT SUBMITTED BY LAKE
TWP. TO
US EPA ON THE
CLEANUP
CHANGES PROPOSED IN
1999.
What
evidence was
presented after
this was issued that caused the Lake Trustees to override these very
strong statements, both legal and technical? It is 6 years later,
and the public still doesn't have this vital information, and
Congressman Regula has told CCLT he is deferring to Lake Township
concerning the Plutonium issue and other man-made radiation that
could impact the area's water supply.
Not long
after this document was sent to US EPA for formal comment, the Twp.
did a 180 degree
turn away
from the legal and technical positions presented in this report.
CCLT and others were stunned and mystified by the dramatic switch.
Because this document makes a strong case that
EPA was
acting arbitrary and capricious, the sudden "flipflop" by the Lake
Trustees after this
report was
submitted was very troubling. They didn't merely change their
position. Trustee
Ruley & her
supporters began viciously attacking our citizens group and experts,
bizarrely
attempting to
discredit us, ironically because CCLT maintained
the
same opinions put forth by
attorneys and technical
experts hired by the Trustees!,
Extremely
puzzled, we wrote Sue Ruley, Twp. Trustee, seeking
concrete
evidence as to what
caused her to suddenly embrace
the polluters' and EPA's opinions. We asked whether she had
new independent information that
supported this switch. (She had been a big proponent of
independent testing vs. the PRPS,
even citing publicly Tom Grumbly's recommendation
regarding double blind studies).
...Ruley's written reply indicated the Twp. Did not possess such
evidence. We wondered, did it have anything to do with the Twp.
being listed as a possible
Third Party Defendant with the
Army and others? When the Justice Dept./US EPA released its
findings from an 8 month secret
investigation into the former landfill owner, Charles Kittinger's
Federal Court testimony
of allegations of the government disposing Plutonium cores into IEL,
CCLT obtained legal
depositions of Mr. Kittinger's testimony. I
In these
depositions, we believe we found additional clues into why the
township may have gone
the other way.
The PRP's attorney raised several key questions about possible
liability issues
regarding
the Twp, And local Health Dept., I.e, the lagoons built at IEL for
liquid disposal and
the
permitting process.
While such
concerns regarding liability may exist, did it justify abandoning
the technical advice put for by Bennett & Williams onbehalf of the
Twp.? (NOTE: We believe
the Bennett/Williams 1999 report included extremely serious
concerns, including, but not limited to, whether LOW FLOW was
properly implemented during sampling, that may have caused
significantly skewed test results for metals, vocs
and radiation - thus
affecting the cleanup - because the 1998 test results were heavily
relied upon in opening:
the Record of
Decision.)
And, if a
potential liability existed, shouldn't Ms. Ruley and others have
recused themselves
regarding the
IEL? Instead, they pushed their new agenda. Didn't this constitute a
possible conflict of interest? A recent Repository article reported
that the Tusc. Watershed
may impact 13
counties. USGS indicated IEL drains toward the Tusc. The health of
thousands of people may be at risk by what is buried in IEL. Yet,
the Twp. even supported
the sealing
of 33 test wells, although the Monitored Natural Attenuation must
rely on such
test wells to
tell what the contamination is doing at the site.
The public has a right to know.
CCLT/IEL
cc:
DOJ, Scott Oelslager, Congressman Brown, public
|
COMMENTS OF THE BOARD OF LAKE TOWNSHIP TRUSTEES ON
THE PROPOSED CHANGES TO THE REMEDY AT THE
INDUSTRIAL EXCESS LANDFILL SUPERFUND SITE
Serious omissions of substantive evidence, mistakes of
fact and_ substantive flaws
in methodology exist in the administrative record
supporting the proposed remedy. As a
result of these mistakes, omissions and methodological
flaws, the United States
Environmental Protection Agency (USEPA) has failed to
consider relevant factors and
relied upon incomplete information in choosing the
remedy for the Industrial Excess
Landfill Superfund Site. No rational connection exists
between the site conditions and
the remedy selected. Its adoption without further site
characterization and assessment of
the short and long term potential for adverse effects to
human health and the
environment, including an epidemiological study, is
arbitrary, capricious and contrary to
law.
Promulgated under the Comprehensive Environmental
Response, Compensation
and.
Liability Act of 1980, 42 U.S.C.A. 9601
et
seq.
(CERCLA), the National
Contingency Plan
("NCP"),
40
CFR Part 300, is the set of regulations establishing the
national procedures and standards for responding to
discharges of hazardous substances
at sites on the National Priorities List ("NPL" or
"Superfund Sites"). The Industrial
Excess Landfill Site located in Uniontown, Ohio, Lake
Township, Stark County Ohio
(IEL) is such a site. Indeed, pursuant to CERCLA § 118
(42) U.S.C.A. 9618) because the
release of hazardous substances from IEL has resulted in
the closing of drinking water
wells, and, as discussed herein, may require the
expansion of the alternate water supply,
this site is high priority.
|
To fulfill its statutory duties and
obligations at IEL, the USEPA must strictly
comply with the procedures and standards set
forth in the NCP during all phases of its
response to the release of hazardous
substances, including the remedial
investigation,
feasibility study, remedy selection,
remedial design and remedial action. To do
otherwise
is contrary to law. In addition, any remedy
selected by the USEPA must comply with
applicable, relevant and appropriate
requirements (ARARs) of state and federal
law. In
making a remedy selection decision, the
USEPA must examine all the relevant data and
articulate a satisfactory explanation for
its action, including a rational connection
between
the facts found and the choice made.
Further, the agency must act in the public
interest.
U.S. v. Akzo Coatings of America, Inn.,
949 F. 2d 1409,1424-1426 (6`h
Cir. 1991);
In
the Matter of
Bell Petroleum Services,3
F. 3d 889, 904 (5`h
Cir. 1993);
Minnesota v. Kalman
W. Abrams Metals, Inc. et al.,
155 F. 3d 1019 (8th Cir. 1998). If an agency
fails to
adequately study the nature and extent of
the contamination problem prior to
implementing a remedy, ignores warnings
regarding the viability of a remedy, or
denies
the public a real opportunity to comment on
a remedy, its remedy selection is arbitrary
and capricious. Kalman W. Abrams Metals,
Inc.
at 1024. Similarly, relying upon an
administrative record containing errors of
procedure and serious omissions of
substantive evidence is arbitrary and
capricious.
Akzo Coatings
at 1425.
Site Characterization and Remedy Selection.
The national goal of the response process
contained in CERCLA and the NCP is
to select remedies that are protective of
human health and the environment, maintain
protection over time and minimize untreated
waste. Remedies should eliminate, reduce,
or control risks to human health and the
environment. (40 CFR 300.430).
|
Remedial
actions in which treatment
permanently and significantly
reduces the volume, toxicity,
mobility and bioaccumulation of
the hazardous substances is
preferred over remedial actions
not involving such treatment (42
CFR § 98621(b), CERCLA §
1221(b)).
To
accomplish these goals, the NCP
establishes a procedure and
program principles,
including use of operable units,
complementary phasing of
remedies, and gathering site
specific data that reflects the scope and complexity of the site
problems being addressed.
The key to identifying and
selecting a remedy and meeting
the program goals and
principles is developing a
conceptual understanding of the
site and its environs. That is
accomplished through a site
characterization to determine
the nature and threat to human
health and the
environment posed by
hazardous
substances and to support the
analysis -and
design of a remedy.
The site characterization is
required to assess (1) the
physical characteristics of the
site (surface features, soils,
geology, hydrogeology,
meteorology and ecology); (2)
the air, surface water and
groundwater; (3) the waste and
its propensity to bioaccumulate,
persist and move in the
environment; (4) exposure
pathways through environmental
media; (5) exposure routes such
as ingestion, inhalation,
absorption through skin and (6)
other factors (40 CFR
§300.430(d)(2)).
The site characterization
requirement is
mandatory. Without it, a
conceptual model of the nature,
transport and fate of the
hazardous substances cannot be
constructed. Without a
conceptual model of what has
and is occurring at the site and
its environs, site-specific
remedial alternatives protective
of local human health and
the environment cannot be
identified.
Development of
remedial alternatives during the
feasibility study and,
ultimately, the implemented
remedy, must be fully
integrated with the site
characterization so that
a
rational
|
connection exists
between the site
conditions and the
remedy selected.
(40 CFR
300.430(e)(1)). In
addition, the USEPA
is required to
identify applicable
relevant and
appropriate
requirements (ARARs)
related to the site
and to incorporate
them into the
remedial design (42
U.S.C.A. § 9621(d),
CERCLA §121(d)).
To select a remedy
without
sufficient site
characterization and
supporting evidence
confirming that the
remedy will protect
human health and the
environment by
permanently and
significantly
reducing the volume,
toxicity, mobility
and bioaccumulation
of the
hazardous substances,
maintain
protection over time
and minimize
untreated waste is
contrary to law and
arbitrary and
capricious.
In this instance,
the USEPA has not
completed a site
characterization
sufficient to
determine the
nature, transport
and fate of
contaminants and to
identify and select
a
remedy meeting the
goals of CERCLA for
the IEL Site.
The report of
Bennett &
Williams (sent
directly to the
USEPA on
April 12, 1999, to
have been attached
as Exhibit A hereto,
complete with its
accompanying
Exhibits), presents
a detailed
discussion of the
mistakes of fact,
serious omissions of
substantive
evidence, flawed
methodology and
errors in scientific
procedures found in
the record. By way
of example only, the
geology
and soils have been
mischaracterized
leading to incorrect
assumptions relating
to
groundwater pH, the
propensity of the
soils to promote
natural attenuation,
contaminant
fate, and transport
and groundwater flow
rates. True
background wells
have never been
established, even
though recommended
by the Science
Advisory Board.
In some instances,
including the 1998
groundwater sampling
done by the PRPs,
the detection
limits used in laboratory analysis of water samples were above the
Maximum
Contaminant Levels (MCLs),
the clean up
standards adopted
for groundwater.
|
The
ATSDR in
its
Health
Consultation
on the
1998
groundwater
data,
criticized
the 1998
data
on this
basis
as
well. It
is
impossible
to
establish
that
groundwater
meets
the MCLs
if the
analytical
method
cannot
even
detect
contaminants
in that
range.
If the
geological
and
hydrogeological
site
characterization
is
flawed,
all
subsequent
work
based
upon it
and
,
the
remedy
selection
will be
flawed,
putting
the
public
health
and the
environment
at risk.
Such is
the case
at IEL.
In the
February
17, 1999
letter
of
William
Munro,
Director
of the
USEPA
Region
V
Superfund
Division
(attached
as
Exhibit
B and
incorporated
herein),
the
USEPA
admitted
that
it
does not
know
the
transport
and fate
of the
tons and
gallons
of
hazardous
substances
that
were
disposed
at the
Industrial
Excess
Landfill.
It does
not know
whether
the
hazardous
substances
have
passed
through
the
monitored
area and
are
continuing
to
spread.
It does
not know
if the
hazardous
substances
have
been
completely
diluted
and
dispersed.
It does
not know
if the
hazardous
substances
have
been
naturally
attenuated.
It
does not
know
if the
hazardous
substances
have
accumulated
at an
undiscovered
location.
All that
the
USEPA
does
know is
that the
levels
of
hazardous
substances
in some
of the
offsite
monitoring
and
residential
wells
may have
decreased
below
the MCLs,
for now.
As
discussed
in the
Bennett
&
Williams
report,
however,
even this conclusion is unfounded. On the other hand, levels of
hazardous
substances
at
other
monitoring
wells
have
increased.
As a
result
of the
incomplete
site
assessment
and
mistakes
of fact
and
flawed
methodologies,
a
conceptual
understanding
of what
mechanism(s)
is
responsible
for the
changing
contaminant
levels
in
offsite
monitoring
wells
does not
exist.
Without
this
knowledge,
a proper
site-specific
remedy
addressing
those
mechanisms,
as
contemplated
by the
NCP,
cannot
be
developed.
Continue
to
Pages
6-12
HOME| MEETING |IEL
TIMELINE| REPORTS |
LETTERS | DOCUMENTS |
ARTICLES | LINKS
|
|
|
|
|
|